August 12, 2023 |
Guilford Park High School Ribbon Cutting Ceremony
|
May 11, 2023 |
|
April 13, 2023 |
|
March 9, 2023 |
|
February 9, 2023 |
|
February 9, 2023 |
BOE It is recommended that the Board of Education approve the name Southeast High School for High School #13 effective February 10, 2023.
Move approval for High School #13 to be named Guilford Park High School. Motion by Jolene Mosley, second by Abisola Ayoola. Final Resolution: Motion Carries Yea: Linfeng Chen, Yun Lu, Jennifer Swickard Mallo, Abisola Ayoola, Jacquelin McCoy, Jolene Mosley, Antonia Watts
|
January 12, 2023 |
|
January 12, 2023 |
BOE Committee recommended that the Board of Education approve the name Quarry Heights High School for High School #13 effective January 13, 2023. |
December 5, 2022 |
|
November 3, 2022 |
|
October 4, 2022 |
|
September 8, 2022 |
|
August 30, 2022 |
Superintendent's Proposed Attendance Area Adjustment Plan |
August 16, 2022 |
|
July 14, 2022 |
|
June 9, 2022 |
|
May 12, 2022 |
|
April 6, 2022 |
|
March 10, 2022 |
|
February 10, 2022 |
|
January 13, 2022 |
|
December 7, 2021 |
|
November 2, 2021 |
|
October 5, 2021 |
|
September 2, 2021 |
|
August 12, 2021 |
|
July 15, 2021 |
|
June 10, 2021 |
|
May 11, 2021 |
|
April 15, 2021 |
BOE HS 13 construction completion status 2022 Capital Budget - Includes pictures on the progress of HS13 |
March 11, 2021 |
|
February 11, 2021 |
|
January 6, 2021 |
|
December 7, 2020 |
|
November 5, 2020 |
|
October 16, 2020 |
Howard County Executive Calvin Ball Announces Troy Park as High School #14 Site Preference Proposed site plan (Track moved to location previously allocated for a Howard County Maintenance Shop) |
October 8, 2020 |
|
October 5, 2020 |
|
September 10, 2020 |
|
August 18, 2020 |
|
July 9, 2020 |
|
June 11, 2020 |
|
May 14, 2020 |
|
April 16, 2020 |
BOE Virtual Meeting: Approved HS 13 bids. Also approved all alternatives (e.g. scoreboards, child development center, photovoltaic system, etc.). Bids & Contracts |
January 16, 2020 |
Progress on Identifying Location of High School #14 Continues as Environmental Assessment Study Released |
December 5, 2019 |
Mission Road Site Development Plan |
December 2, 2019 |
County Council Legislative Session: Approval of Council Bill 145-2019 granting setback and height variances for the 13th high school. |
October 7, 2019 |
Transfer of county property to Howard County Public School System. |
September 19, 2019 |
BOE - Regular Meeting: Video of presentation (scroll down to link 7.C) of High School #13 Construction Document Report Learned new school road will be called Ridgely’s Run Rd. |
September 12, 2019 |
Land purchased from Chase Land, LLC. |
August 22, 2019 |
Preliminary map showing two boundary considerations for HS 13 (presented during the 2020-2021 Attendance Area Adjustment Plan to the BOE). NOTE: Alternative 1 would allow the school to have NO walkers. |
May 7, 2019 |
Howard County Times: Howard lawmakers vote to allow county to enter into agreement to build 13th high school in Jessup |
May 6, 2019 |
County Council Legislative Session: Council Resolution 49-2019 - A RESOLUTION approving and authorizing the execution of a Development Rights and Responsibilities Agreement by Chase Land, LLC, a Maryland Limited Liability Company, Annapolis Junction Holdings, LP, a Maryland Limited Partnership (video) |
April 30, 2019 |
Howard County Times: Howard lawmakers, Board of Education express skepticism over school purchasing agreement |
April 29, 2019 |
County Council Legislative Work Session: Development Rights and Responsibilities Agreement by Chase Land, LLC (video) |
April 15, 2019 |
Howard County Times: Howard County Board of Education recommends amending purchasing agreement for new high school in Jessup |
April 10, 2019 |
Howard County Times: Howard County school purchasing agreement draws skepticism from lawmakers and activists |
March 22, 2019 |
Howard County Times: Howard County Executive Calvin Ball moves one step closer to building 13th high school |
March 21, 2019 |
County Executive Ball Pre-files Bill to Advance Construction of High School #13 |
March 15, 2019 |
Howard County Times: Howard Board of Education approves design for 13th high school |
March 14, 2019 |
|
January 28, 2019 |
Video of quarterly county council meeting with the Board of Education Discussion of High School #13 and #14 as well as Elementary School #43 at Mission Road. Also includes a discussion on school sidewalks. |
December 19, 2018 |
Chase Land, LLC and Annapolis Junction Holdings, LP, Petition for Development Rights and Responsibilities Agreement and attachment received by Howard County Council and addressed to county executive Calvin Ball. |
November 26, 2018 |
Community Meeting - New Road for High School #13 (video) (picture) |
November 13, 2018
|
Community Meeting - Chase Land, LLC Development Right and Responsibilities Agreement |
November 2, 2018 |
Howard County Times: Two Sites Suggested for Future Elkridge High School (HS #14) |
September 20, 2018 |
High School #13 Schematic Design Report |
September 20, 2018 |
BOE Regular Meeting (video) Presentation of HS13 schematic design report to BOE (scroll down and click on 7.D link). |
September 14, 2018 |
Purchase and Sale Agreement between Howard County and Chase Land, LLC |
March 12, 2018 |
Columbia Flyer: Jessup property picked for next Howard County high school |
March 8, 2018 |
BOE Regular Meeting (video) Vote to choose HS#13 school site (scroll down and click on 7.D link). PowerPoint slides presented prior to vote. |
March 8, 2018 |
HCPSS News: HCPSS Board of Education Selects Mission Road Site for High School #13 |
March 5, 2018 |
Mission Road Vibration, Noise, and Ambient Air Monitoring Report |
March 1, 2018 |
|
February 12, 2018 |
Howard County Times: New tests planned on Jessup land being considered for high school |
February 8, 2018 |
BOE Regular Meeting (video) Contains interviews with environmental experts on Mission Rd. Scroll down and click on 14.B link “High School #13 Site Selection (Bruce Gist/Renee Kamen) - REPORT” This is our meeting minutes from that video. Site Selection – New HS #13 PowerPoint Slides Kittleman's letter to BOE regarding High school #13 site selection |
February 7, 2018 |
High School #13 Site Selection Shows proposed sites for Mission Rd. and Troy Park (with and without use of the White property) |
February 2, 2018 |
Columbia Flyer: Superintendent says window to open new Howard County high school by 2022 is closing |
February 1, 2018 |
HS13 Community Meeting: Q&A (Cell Phone Video) |
February 1, 2018 |
|
January 30, 2018 |
BOE Quarterly Meeting: Location and next steps for High School #13 opening in 2022 (Video) |
January 29, 2018 |
Kittleman presented draft site plan for high school at Troy Park |
January 24, 2018 |
Started petition for High School #13 to be put in Jessup |
January 17, 2018 |
Columbia Flyer: As Questions Swirl Around Search For a Howard County High School Site, A Third Property Is Studied |
January 12, 2018 |
Kittleman announces Troy Park for HS 13 consideration (letter) |
January 11, 2018 |
BOE Meeting (video): Reconsiders Mission Rd. Site - scroll down to 7.D link Kittleman’s letter to BOE to reconsider Mission Rd. Site |
January 8-9, 2018 |
Why Not Jessup Facebook group and this web site created. |
January 3-5, 2018 |
After a closed door meeting, the Board of Education announces they have ruled out both the Rockburn and Mission Rd. sites as candidates for HS 13. |
December 22, 2017 |
Letter: Kittleman rules out Rockburn Park site Rockburn High School 13 Proposed Site Map |
December 11, 2017 |
Columbia Flyer: New Sites Possible for High School 13, Residents Petition Rockburn Location |
November 2, 2017 |
Columbia Flyer: Conservationists ask Howard County to Swap Park Land in Rockburn Park for New High School |
October 20, 2017 |
Mission Road Site Analysis Report |
October 19, 2017 |
Baltimore Sun: The Right Fit For A New High School [Editorial] |
October 17, 2017 |
Phase 1 Environment Site Assessment for Rockburn Branch Park |
October 12, 2017 |
Howard County Times: Howard School System Accelerating Search for High School 13 Site |
October, 2017 |
Phase 1 Environmental Site Assessment Report Data Gap Resolution Addendum to November 2016 report - includes Parcel 349, an 8.2-acre wooded residential parcel addressed as 8717 Mission Road. |
July 17, 2017 |
HCPSS: Update on environmental studies and progress on potential Elkridge sites |
July, 2017 |
Mission Rd. Ambient Air Quality Testing Report |
May, 2017 |
|
April 25, 2017 |
Chase Properties Pre-Submission Meeting Minutes Discusses the proposed Site Development Plan for site grading and tree clearing for the Mission Rd. Site. Mission Road Chase Property Environmental Concept Plan |
November, 2016 |
|
October 4, 2016 |
BOE Meeting: Mission Road Site Acquisition Public Hearing (Video) |
September 8, 2016 |
BOE Report: Potential land aquisition for Turf Valley elementary school and Mission Road schools |
September 7, 2016 |
BOE Meeting: Site acquisition for Turf Valley elementary school and Mission Road schools (Video) |
May 6, 2016 |
Howard County Government: Kittleman signs agreement to purchase site for county’s 13th high school Howard County Times: Howard Moves Forward on $23 Million Land Purchase For New High School In Jessup |
October 13, 2014 |
Rock Road Recycle: Savage Stone’s Jessup, MD plant is “Picture Perfect!” |
January 25, 2004 |
Baltimore Sun: State grants permit for 545-acre quarry |
September 10, 2003 |
Troy Hill Geophysical Site Survey Results Phase II |
January 25, 2001 |
Troy Hill Limited Phase II Soil and Surface Water Investigation |
May, 1999 |
Troy Hill Phase 1 Environmental Site Assessment |
May 24, 1996 |
Baltimore Sun: Architect Shows Board Benefits of Quarry Parks, Homes Could Be Built On Land After Mining |
January 5, 1996 |
|
June 3, 1994 |
Baltimore Sun: Residents OK Quarry in Jessup |